Optimum Consulting Is Concerned About the Maximum Project Time in One

Question 19

Multiple Choice

Optimum consulting is concerned about the maximum project time in one of their project management models.Using simulation,they found an estimate of the maximum project time to be about 364 days.To better understand the variability,Optimum consulting has used ________ that estimated the accuracy of the forecast statistics shown in the statistics view of the simulation results.


A) Scenario Analysis tool
B) Decision Table tool
C) 2D Simulation tool
D) Bootstrap tool

Correct Answer:

verifed

Verified