menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Achieving Competitive Advantage Study Set 2
  4. Exam
    Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path
  5. Question
    The Amount of Time an Activity May Be Delayed from Its
Solved

The Amount of Time an Activity May Be Delayed from Its

Question 118

Question 118

Multiple Choice

The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:


A) delay.
B) float.
C) late start.
D) late finish.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q15: The late start time should be calculated

Q65: A backward pass is performed when it

Q85: Hammock activities break a task into greater

Q98: What are hammock activities and when should

Q108: A project's duration can be reduced by:<br>A)shortening

Q109: A project has the precedence requirements and

Q110: A project has the precedence requirements and

Q115: Construct a network using the information in

Q116: The longest route through the network is

Q117: Use the values in the table to

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines