Multiple Choice
Based on the activity network pictured,what is the best statement?
A) Activity C is a burst activity.
B) Activity E has one predecessor,Activity B.
C) Activity A and Activity C are merge activities.
D) There are no serial activities in this network.
Correct Answer:

Verified
Correct Answer:
Verified