A Project Has the Precedence Requirements and Activity Durations Shown

Question 56

Multiple Choice

A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity? A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?   A) 11,30 B) 7,24 C) 11,24 D) 7,36


A) 11,30
B) 7,24
C) 11,24
D) 7,36