Multiple Choice
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?
A) 11,30
B) 7,24
C) 11,24
D) 7,36
Correct Answer:

Verified
Correct Answer:
Verified
Q29: What is the background of CPM and
Q44: The variance of an activity is given
Q51: What is the late finish time for
Q52: There is no slack on the project
Q53: Use the network diagram and activity lengths
Q54: Activities C,D,and E in the project represented
Q55: What is the slack time for Activity
Q58: Based on the activity network pictured,what is
Q59: An activity has a pessimistic time that
Q61: What is the late start time for