    What Is the Slack Time for Activity C Given the Activity
Solved

What Is the Slack Time for Activity C Given the Activity

Question 55

Question 55

Multiple Choice

What is the slack time for Activity C given the activity times and precedence requirements shown in the table? What is the slack time for Activity C given the activity times and precedence requirements shown in the table?   A) 2 B) 1 C) 0 D) 3


A) 2
B) 1
C) 0
D) 3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q29: What is the background of CPM and

Q44: The variance of an activity is given

Q50: Use the network diagram and activity lengths

Q51: What is the late finish time for

Q52: There is no slack on the project

Q53: Use the network diagram and activity lengths

Q54: Activities C,D,and E in the project represented

Q56: A project has the precedence requirements and

Q58: Based on the activity network pictured,what is

Q59: An activity has a pessimistic time that

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines