If a Project Activity Experiences Negative Variation

Question 16

Multiple Choice

If a project activity experiences negative variation:


A) the following activity can be started earlier than anticipated.
B) the following activity must be started later than anticipated.
C) the preceding activity must be started later than anticipated.
D) the preceding activity can be started earlier than anticipated.