Multiple Choice
Your next project consists of 10 consecutive 8-day activities,each estimated by a different worker in your organization.Note that the estimators have not yet added any buffer to the 8-day figure.Your organizational culture dictates that you add your own safety margin of 30% into your estimates.The new project manager has just completed an excellent course in project management offered at the local university.When the first project meeting begins,he dazzles you with his wit and sophistication.You are considerably less charmed when he reveals that he has an exciting new technique for managing projects.He adheres to critical chain project management ideas and plans to create an overall project safety buffer after trimming the safety buffers from each of the 10 activities.How much closer has the project deadline moved?
A) 12 days
B) 6 days
C) 18 days
D) 9 days
Correct Answer:

Verified
Correct Answer:
Verified
Q46: A project that consists of six
Q47: Which of these numerical (quantity)comparisons is CORRECT?<br>A)Scrum
Q48: Which of the following statements about CCPM
Q49: A project consists of four consecutive
Q50: Your next project consists of 8 consecutive
Q52: Compose a haiku using three or more
Q53: A system-wide constraint is called a:<br>A)Rope.<br>B)Resource.<br>C)Drum.<br>D)Chain.
Q55: What are the key elements of extreme
Q56: Which statement about critical chain project management
Q74: The one element that Agile shares with