The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

Question 62

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the critical path for the project consists of activities A) A-B-C-D-E. B) A-B-C-E. C) A-B-D-E. D) A-B-C-D.
Table 9.2
-Using Table 9.2,the critical path for the project consists of activities


A) A-B-C-D-E.
B) A-B-C-E.
C) A-B-D-E.
D) A-B-C-D.

Correct Answer: