Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the critical path for the project consists of activities
A) A-B-C-D-E.
B) A-B-C-E.
C) A-B-D-E.
D) A-B-C-D.
Correct Answer:

Verified
Correct Answer:
Verified