Multiple Choice
A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days) shown in the table below.Complete the table and determine the expected completion time for the project.
A) 17 days
B) 18 days
C) 21 days
D) 19 days
Correct Answer:

Verified
Correct Answer: