Multiple Choice
Task X has an 82 percent probability that it will be completed in 20 days or less.The standard deviation of its duration is five days.What is its expected duration?
A) 15.4 days
B) 15.9 days
C) 19.1 days
D) 12.3 days
Correct Answer:

Verified
Correct Answer:
Verified