    Task X Has an 82 Percent Probability That It Will
Solved

Task X Has an 82 Percent Probability That It Will

Question 27

Question 27

Multiple Choice

Task X has an 82 percent probability that it will be completed in 20 days or less.The standard deviation of its duration is five days.What is its expected duration?


A) 15.4 days
B) 15.9 days
C) 19.1 days
D) 12.3 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q22: A project manager has discovered that three

Q23: Annie is planning a large surprise party

Q24: A project manager has discovered that three

Q25: Task X has a best-case duration of

Q26: Given the tasks,estimated durations,and crash costs shown

Q28: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB7860/.jpg" alt=" Identify

Q29: An estimate of the duration of a

Q30: Task X has a most likely duration

Q31: For a project with many task paths

Q32: A simple sequential project (each task must

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines