Multiple Choice
Identify the critical path to completion for the project plan.
A) A,C,D,F is 45 hours.
B) A,B,C,D,E,F is not a path.
C) A,B,E,F is 46 hours.
D) A,B,D,F is 49 hours
Correct Answer:

Verified
Correct Answer:
Verified