Multiple Choice
A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below: What is the likelihood the project will be completed in 10 days?
A) Between 88 and 88 percent
B) Between 89 and 92 percent
C) Between 93 and 97 percent
D) Between 98 and 100 percent
Correct Answer:

Verified
Correct Answer:
Verified