Multiple Choice
Given the tasks,estimated durations,and crash costs shown below,what is the total cost of the steps needed to provide the cheapest way to reduce the project length by three days?
A) $2,800
B) $2,500
C) $1,100
D) $2,300
Correct Answer:

Verified
Correct Answer:
Verified