Multiple Choice
Jones Company uses widgets as component parts.In a particular week it has gross requirements for 250 units of widgets,beginning inventory of 50 widgets,and scheduled receipts of 350 widgets.Available inventory for the next period is:
A) 650.
B) 50.
C) 250.
D) 150.
Correct Answer:

Verified
Correct Answer: