Question 21
Multiple Choice
Demand-driven MRP:
Question 22
Multiple Choice
The available capacity of a worker,machine,work center,or facility during a specific period of time is compared against the capacity needed for a specific work schedule in a:
Question 23
Multiple Choice
If the planning horizon is 12 weeks,the cumulative lead time must be:
Question 24
Multiple Choice
An MRP schedule is as follows.What are the net requirements in week 2?
Question 25
Multiple Choice
A master production schedule shows the beginning inventory is 200 units,the forecast is 600 units,and the actual customer orders is 500 units.Using a lot-for-lot rule,what is the MPS quantity for period 1?
Question 26
Multiple Choice
Benefits of ERP systems include all of the following EXCEPT:
Question 27
Multiple Choice
Capacity requirements planning does all of the following EXCEPT:
Question 28
Multiple Choice
The quantities of end items to be completed in each time period into the future is shown in a(n) :
Question 29
Multiple Choice
The planned order releases in week 5 are 10 units.Each unit must be processed for five minutes at the workstation.If the available capacity at the workstation is one hour:
Question 30
Multiple Choice
An MPS shows:
Question 31
Multiple Choice
Jones Company uses widgets as component parts.In a particular week it has gross requirements for 250 units of widgets,beginning inventory of 50 widgets,and scheduled receipts of 350 widgets.Available inventory for the next period is:
Question 32
Multiple Choice
The longest lead-time path in the BOM is the:
Question 33
Multiple Choice
Materials requirements planning (MRP) systems are used primarily to:
Question 34
Multiple Choice
A master production schedule shows the following information:
Based on the information in the MPS,what is the number of items that is available to promise in week 4?
Question 35
Multiple Choice
The entire time period covered by the MPS is the:
Question 36
Multiple Choice
A master production schedule shows the beginning inventory is 40 units,the forecast is 100 units,and actual customer orders are 80 units.What is the quantity that is available to promise in period 1?