Multiple Choice
The planned order releases in week 5 are 10 units.Each unit must be processed for five minutes at the workstation.If the available capacity at the workstation is one hour:
A) Overtime will be needed.
B) Delivery lead times should be increased.
C) The workstation is underloaded.
D) An order backlog will be created.