Capacity requirements planning does all of the following EXCEPT:
A) Determine if a work center has the capacity to implement the MRP plan.
B) Use planned order releases and scheduled receipts to estimate work center loads.
C) Develop a load profile.
D) Recalculate the MRP plan.