True/False
The duration of an entire project is determined by the earliest finish time (EF) for the last activity on the critical path.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q37: To obtain the latest start and latest
Q40: A(n) _ chart is a project schedule
Q43: Activity slack refers to how much time
Q44: The crash cost is the additional cost
Q46: The difference between the earliest start (ES)
Q48: A project has three paths. A- B-
Q49: Which of the following statements concerning the
Q50: Explain what it means to crash activities
Q69: The _ is a statement of all
Q108: A project is an interrelated set of