Multiple Choice
Table 3.1
Time (weeks)
-Using Table 3.1,if the expected times for activities A,G,and H increased by 2,3,and 4 weeks,respectively,by how many weeks would the project's earliest expected time of completion increase?
A) less than or equal to 2 weeks
B) greater than 2 weeks but less than or equal to 4 weeks
C) greater than 4 weeks but less than or equal to 6 weeks
D) greater than 6 weeks
Correct Answer:

Verified
Correct Answer:
Verified
Q17: Typically activities along the critical path have
Q39: The _ is the longest estimated time
Q45: The duration of an entire project is
Q90: Before beginning to create a PERT/CPM network
Q92: The probability that a project will be
Q96: Table 3.5<br> <span class="ql-formula" data-value="\begin{array}
Q97: Table 3.7<br> <span class="ql-formula" data-value="\begin{array}
Q98: Table 3.7<br> <span class="ql-formula" data-value="\begin{array}
Q100: Table 3.3<br> <span class="ql-formula" data-value="\begin{array}
Q103: Each activity in the work breakdown structure