Multiple Choice
Table 3.8
-Using Table 3.8,what is the earliest completion time of the project?
A) less than or equal to 10 weeks
B) greater than 10 weeks but less than or equal to 13 weeks
C) greater than 13 weeks but less than or equal to 16 weeks
D) greater than 16 weeks
Correct Answer:

Verified
Correct Answer:
Verified
Q14: Network methods let project managers analyze the
Q18: Assume that activity G has the following
Q18: Draw the network corresponding to the
Q20: Table 3.13<br>You are responsible for managing
Q22: Table 3.4<br> <span class="ql-formula" data-value="\begin{array}
Q25: If a project has multiple critical paths,which
Q27: Explain how cost-time tradeoffs should be analyzed
Q31: The _ is the sequence of activities
Q52: In an activity-on-node [AON] network,the nodes represent
Q111: A hierarchical approach to developing a work