Table 38 -Using Table 3

Question 23

Multiple Choice

Table 3.8
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 3 B 4 C A,B5 D  A 6 E C4 F D,E2\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 3 \\\text { B } & \cdots & 4 \\\text { C } & A , B & 5 \\\text { D } & \text { A } & 6 \\\text { E } & \mathrm { C } & 4 \\\text { F } & \mathrm { D } , \mathrm { E } & 2 \\\hline\end{array}
-Using Table 3.8,what is the earliest completion time of the project?


A) less than or equal to 10 weeks
B) greater than 10 weeks but less than or equal to 13 weeks
C) greater than 13 weeks but less than or equal to 16 weeks
D) greater than 16 weeks

Correct Answer: