Multiple Choice
Table 3.13
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 3.13,if the expected time for activity E is decreased to 8 weeks,what is the new expected completion time for the project?
A) 31 weeks or less
B) 32-33 weeks
C) 34-35 weeks
D) more than 35 weeks
Correct Answer:

Verified
Correct Answer:
Verified