    A Project Consists of Four Activities with Information as Shown
Solved

A Project Consists of Four Activities with Information as Shown

Question 86

Question 86

Multiple Choice

A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project? A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project?   A)  24 B)  18 C)  8.41 D)  4.24


A) 24
B) 18
C) 8.41
D) 4.24

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q17: Goldratt's solution to the variables involved in

Q42: Wayne and Garth are engaged in XP

Q44: Agile project management features a logical series

Q50: Your next project consists of 8 consecutive

Q56: Which statement about critical chain project management

Q66: Once the organization elevates its constraint,its system

Q82: A project consists of four activities with

Q87: A project is represented by the activity

Q89: Wayne and Garth are engaged in XP

Q105: Your boss catches you at the water

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines