Multiple Choice
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many feeder buffers are needed if this project is managed using critical chain methodology?
A) 0
B) 1
C) 2
D) 3
Correct Answer:

Verified
Correct Answer: