Multiple Choice
Which of the following statements concerning the critical path in project network is FALSE?
A) The critical path is the sequence of activities between a project's start and finish that takes the longest to finish.
B) Activities on the critical path have zero slack.
C) Delaying an activity on the critical path delays the entire project.
D) There is always only one critical path in a project network.
Correct Answer:

Verified
Correct Answer:
Verified