Multiple Choice
The difference between the earliest start (ES) and the earliest finish (EF) times for any activity in a project network is the
A) estimated duration of the activity.
B) latest finish time for the activity.
C) activity total slack time.
D) activity free slack time.
Correct Answer:

Verified
Correct Answer:
Verified