A project has three paths. A- B- C has a length of 25 days. A- D- C has a length of 15 days. Finally, A- E- C has a length of 20 days. Which one of the following statements is TRUE?
A) A- B- C has the most slack.
B) The expected duration of this project is 25 days.
C) The expected duration of this project is 25 + 15 + 20 = 60 days.
D) A- D- C is the critical path.
Correct Answer:

Verified
Correct Answer:
Verified