____________Is a Scheduling Technique That Requires Greater Cost and Schedule

Question 59

Multiple Choice

____________is a scheduling technique that requires greater cost and schedule refinement regarding upcoming activities in the project schedule.


A) Cone of uncertainty
B) Rolling wave planning.
C) Uncertainty reduction
D) Tornado analysis

Correct Answer: