Multiple Choice
Variances can be caused by:
I. Out-of-control operations
II. Better-than-expected operations
III. Inappropriate benchmarks
A) I and III only
B) II and III only
C) I and II only
D) I, II, and III
Correct Answer:

Verified
Correct Answer:
Verified