Solved

A Shop Order for 1000 Pieces Is to Be Processed

Question 14

Multiple Choice

A shop order for 1000 pieces is to be processed on work station 123. The setup time is 4 hours and the run time per piece is .08 hours. What is the required capacity on this work center in standard hours?


A) 4.08
B) 0.08
C) 80
D) 84
E) 4000