Multiple Choice
Which of the following statements is best?
A) a bottleneck (capacity constraint resource) will control the throughput of all products processed by it
B) a time buffer should be established before a bottleneck
C) work centers feeding a bottleneck should work at full capacity
D) a and b are true
E) b and c are true
Correct Answer:

Verified
Correct Answer:
Verified