Multiple Choice
Which of the following are methods of reducing manufacturing lead time?
I. Subcontracting
II. Forward scheduling
III. Operation overlapping
IV. Operation splitting
A) all of the above
B) I and II
C) I and III
D) II and III
E) III and IV
Correct Answer:

Verified
Correct Answer:
Verified