__________Refers to Reducing the Total Time to Complete the Project

Question 5

Multiple Choice

__________refers to reducing the total time to complete the project to meet a revised due date.


A) Benchmarking
B) Crashing a project
C) Project resource leveling
D) Activity sequencing

Correct Answer: