Multiple Choice
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWP for Activity C?
A) $0 − $5K
B) $5.01K − $10K
C) $10.01K − $15K
D) $15.01K − $20K
E) Over $20K
Correct Answer:

Verified
Correct Answer:
Verified
Q83: Derivative projects are those that address incremental
Q84: A project has four activities: A, B,
Q85: Earned value management (EVM) is a technique
Q86: The activity direct costs associated with a
Q87: Pieces of work within a project that
Q89: In a CPM analysis, if you subtract
Q90: The critical path of activities in a
Q91: You have just been assigned to oversee
Q92: Here are the data for a time-cost
Q93: Popular project management software used in mid-sized