Multiple Choice
The critical path for the network activities shown below is ________ with duration ________.
A) A-D-E; 11
B) B-E; 7
C) B-D-E; 13
D) A-C-E; 6
E) B-C-E; 8
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q121: If an activity whose normal duration is
Q122: The control of projects involves close monitoring
Q123: A simple CPM network has three activities,
Q124: The _ is the computed longest time
Q125: A local project being analyzed by PERT
Q126: The project organization works best when which
Q127: Agile project management is a type of
Q128: Analysis of a PERT problem shows the
Q129: _ is decreasing activity time in a
Q131: Project managers often use the waterfall approach