Multiple Choice
A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of B and of C. B is an immediate predecessor of D and of E. C is an immediate predecessor of E. Which of the following statements is TRUE?
A) There are two paths in this network.
B) There are four paths in this network.
C) There are five paths in this network.
D) There are three paths in this network.
E) There are six paths in this network.
Correct Answer:

Verified
Correct Answer:
Verified
Q97: A project organization works best for an
Q98: Two activities on the same critical path
Q99: A PERT project has 45 activities, 19
Q100: Which of the following statements regarding CPM
Q101: Describe some of the challenges faced in
Q103: If an activity whose normal duration is
Q104: The _ has established a code of
Q105: Project managers have their own code of
Q106: Every network has at most one critical
Q107: The standard deviation of project duration is