Multiple Choice
Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.
A) One; $800
B) One; $6,800
C) Two; $500
D) Two; $5,000
E) One or Two should be crashed; $1,300
Correct Answer:

Verified
Correct Answer:
Verified
Q93: The critical path for the network activities
Q94: A network has been crashed to the
Q95: The bell curve is often appropriate for
Q96: Activity D on a CPM network has
Q97: A project organization works best for an
Q99: A PERT project has 45 activities, 19
Q100: Which of the following statements regarding CPM
Q101: Describe some of the challenges faced in
Q102: A simple CPM network has five activities,
Q103: If an activity whose normal duration is