Multiple Choice
If an activity whose normal duration is 13 days can be shortened to 11 days for an added cost of $1,500, what is the crash cost per period?
A) $500
B) $1,500
C) $750
D) $13,000
E) $15,000
Correct Answer:

Verified
Correct Answer:
Verified