Multiple Choice
Which of the following statements regarding CPM networks is TRUE?
A) There can be multiple critical paths on the same project, all with different durations.
B) The early finish of an activity is the latest early start of all preceding activities.
C) The late start of an activity is its late finish plus its duration.
D) If a specific project has multiple critical paths, all of them will have the same duration.
E) None of these are true.
Correct Answer:

Verified
Correct Answer:
Verified
Q95: The bell curve is often appropriate for
Q96: Activity D on a CPM network has
Q97: A project organization works best for an
Q98: Two activities on the same critical path
Q99: A PERT project has 45 activities, 19
Q101: Describe some of the challenges faced in
Q102: A simple CPM network has five activities,
Q103: If an activity whose normal duration is
Q104: The _ has established a code of
Q105: Project managers have their own code of