Multiple Choice
A key distinction between a risk response and a contingency plan is
A) a risk response is established only for moderate risks while contingency plans are established for major risks.
B) a risk response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan goes into effect only after the risk has transpired.
C) a risk response is only effective when you are able to assess the likelihood of the risk and its impact on the project; all other risks are covered by contingency planning.
D) a risk response is created by the project team and the project manager while the project manager and the customer agree on the contingency plan.
E) a risk response is action that is the response to a risk once it has happened and the contingency plan is created by the customer if the risk response fails.
Correct Answer:

Verified
Correct Answer:
Verified
Q71: Which of the following is the first
Q72: This response is used to remove any
Q73: If, during risk response development, you successfully
Q74: A list of questions that address traditional
Q75: Which verb best characterizes the concept of
Q77: Purchasing an accident insurance policy would be
Q78: A _ (responsible for the work package)
Q79: The _ matrix is divided into red,
Q80: The measurement of how easy it would
Q81: One of the following five choices is