Multiple Choice
The measurement of how easy it would be to detect that the event was going to occur in time to take mitigating action (i.e., how much warning time we would have) is known as __________.
A) risk measurement
B) mitigation
C) risk assessment
D) detection difficulty
E) detection measurement
Correct Answer:

Verified
Correct Answer:
Verified