Multiple Choice
One of the following five choices is NOT involved in risk control. Which choice is it?
A) Executing the risk response strategy
B) Initiating contingency plans
C) Establishing a change control system
D) Establishing contingency funds
E) Watching for new risks
Correct Answer: