A ____________ (responsible for the work package) involved in risk assessment and mitigation will help focus attention on all aspects of risk management.
A) project manager
B) line person
C) stakeholder
D) team leader
E) project sponsor
Correct Answer:

Verified
Correct Answer:
Verified