Multiple Choice
When an activity with a long duration is broken into smaller segments so that the following activities can begin sooner it is called __________.
A) stair-casing
B) waterfalling
C) laddering
D) stair-stepping
E) segmentation
Correct Answer:

Verified
Correct Answer:
Verified