Multiple Choice
A project manager is looking over the actual results of projects and comparing them to what was estimated. She notices that the projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is she recognizing?
A) Padding estimates
B) Project duration
C) Project structure
D) People
E) Organization culture
Correct Answer:

Verified