Multiple Choice
The top-down method for estimating project time and cost that uses weighted variables based on major parameters and is frequently used in the development of software is known as the ____________ method.
A) ratio
B) consensus
C) apportion
D) function point
E) learning curves
Correct Answer:

Verified
Correct Answer:
Verified