The Top-Down Method for Estimating Project Time and Cost That

Question 62

Multiple Choice

The top-down method for estimating project time and cost that uses weighted variables based on major parameters and is frequently used in the development of software is known as the ____________ method.


A) ratio
B) consensus
C) apportion
D) function point
E) learning curves

Correct Answer: