Multiple Choice
The estimating factor that considers the prevailing belief in some firms that detailed estimating takes too much time and is not worth the effort is an example of the ___________ factor.
A) project complexity
B) planning horizon
C) people
D) organizational culture
E) padding estimates
Correct Answer:

Verified
Correct Answer:
Verified