True/False
A dummy activity is an activity inserted into the network diagram to show a precedence relationship, but does not represent any passage of time.
Blooms: Comprehension
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q2: Because the critical path is the shortest
Q3: Project control involves monitoring a project and
Q9: Indirect costs always increase as a project's
Q13: A project consists of the following activities:<br>
Q22: Which of the following is the universal
Q38: A bar graph displaying when activities are
Q53: A standard procedure for numerically measuring a
Q71: Explain project crashing and time-cost tradeoffs, including
Q75: The following table of probabilistic time estimates
Q77: Discuss features of the project planning process,