    A Dummy Activity Is an Activity Inserted into the Network
Solved

A Dummy Activity Is an Activity Inserted into the Network

Question 73

Question 73

True/False

A dummy activity is an activity inserted into the network diagram to show a precedence relationship, but does not represent any passage of time.
Blooms: Comprehension

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q2: Because the critical path is the shortest

Q3: Project control involves monitoring a project and

Q9: Indirect costs always increase as a project's

Q13: A project consists of the following activities:<br>

Q22: Which of the following is the universal

Q38: A bar graph displaying when activities are

Q53: A standard procedure for numerically measuring a

Q71: Explain project crashing and time-cost tradeoffs, including

Q75: The following table of probabilistic time estimates

Q77: Discuss features of the project planning process,

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines