The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, the probability that the project could be completed in 34 weeks or less is approximately
A) 0.86.
B) 0.89.
C) 0.91.
D) 0.96.