Question 75

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
The following table of probabilistic time estimates (in weeks)  and activity predecessors are provided for a project. Table 9.3   -Using Table 9.3, the probability that the project could be completed in 34 weeks or less is approximately A)  0.86. B)  0.89. C)  0.91. D)  0.96.
-Using Table 9.3, the probability that the project could be completed in 34 weeks or less is approximately


A) 0.86.
B) 0.89.
C) 0.91.
D) 0.96.