Multiple Choice
A ______________ breaks down a project into components,subcomponents,activities,and tasks.
A) work breakdown structure (WBS)
B) scope statement
C) responsibility assignment matrix (RAM)
D) organizational breakdown structure (OBS)
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q12: A Gantt chart provides a visual display
Q32: In general,the latest finish time for an
Q36: Crashing activates with positive slack reduces a
Q62: The following table of probabilistic time estimates
Q66: The estimated variance for an activity with
Q66: A project consists of the following four
Q68: The following table of probabilistic time estimates
Q69: A project consists of the following four
Q87: The _ is a document that provides
Q94: Earned value analysis reports a project's performance