Multiple Choice
This example has level resources of three resources for eight days.If the project is limited to two resources, how should the project be organised to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.
A) Paths would be 1,2,3,5 and 1,2,4
B) Paths would be 1,2,3,4 and 1,2,5
C) Paths would be 1,2 and 3,4,5
D) Path would be 1,2,3,4,5
Correct Answer:

Verified
Correct Answer:
Verified
Q8: A resource requirements plan illustrates<br>A)who is responsible
Q9: When several activities need the same limited
Q10: Why are activities drawn in a serial
Q10: Given this project and the requirement that
Q11: Resource utilisation charts based on each activity's
Q16: Resource utilisation charts based on each activity's
Q17: If resources are to be considered in
Q18: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8900/.jpg" alt=" -Resource levelling, or
Q32: Select which of the following does not
Q39: In resource-limited scheduling, the lower priority activities